Kitchen Design and Blueprint
PROJECT TIMELINE & PAYMENTS
Step 1:
Select your finishes:
• Cabinets
• Quartz countertop
• Sink
• Knobs, handles, and pulls
Schedule on-site design session: $350
• Viewing of selected kitchen cabinet sample
• Take room measurements
• Delivery of blueprints for your review (up to three modifications included)
Payment Schedule
- Example Package: 12 cabinets for $12,000 includes:
• Blueprints
• Project management and support
• Prepare site with dust containment and surface protection
• Demolition
• Delivery of cabinets
• Install cabinets
• Install quartz countertop
• Install sink
• Install knobs, handles, and pulls
• Disposal of all garbage and debris to an off-site facility - Cost for Additional Cabinets: $1,000 per cabinet.
• 13 cabinets = $13,000
• 14 cabinets = $14,000
• 15 cabinets = $15,000
• 20 cabinets = $20,000
• … and so on
Step 2:
• Sign the contract
• Deposit amount: 20%
Example: For a 12 cabinet ($12,000) package, the deposit will be $2,400
Step 3:
Construction Day 1:
• Dust containment
• Demolition
• Progress payment: 20%
Construction Day 2:
• Install cabinets
• Install cabinet knobs, handles, and pulls
• Progress payment: 20%
Construction Day 3:
• Install quartz countertop
• Install sink
• Progress payment: 20%
Construction Day 4:
• Final installation
• Cleaning
• Progress payment: 20% (Final balance)
Construction Day 5+ (Optional):
• Additional options selected and scheduled for your remodeling project
Contact Us:
Call/Text: 800-939-1960
Email: office@bumvar.com